Marine technology company VEEM approached us to construct a large assembly hall for future testing specialist equipment, as well as a two-storey office block. Assisting with the design stage, we commissioned engineering firm DWA Consulting to collaborate on the project.
Year of completion |
2020 |
Project size |
4,223 m2 |
Project value |
$2m |
Engineering firm |
DWA Consulting |
Project Deliverables
• Assembly hall
• Two-storey office block
• Staff room kitchen
• Company boardroom
• Change room and toilets
• Carpark
Our Solutions
Higher Quality, Lower Cost
To provide a higher quality result for a lower cost, we switched the proposed steel building materials out for concrete alternatives, using local suppliers to further reduce cost.
Adaptable Approach
As the factory fit out was designed for a very specific purpose, there were requests for design changes throughout construction. We quickly adapted our approach and completed the variations as required.
Fully Finished Fit Out
Upon project completion, every aspect of the build had been managed for the client, allowing them to move in their equipment and commence operations right away.